From January 2027, distribution charges for HV and EHV supply points are calculated differently

From 1 January 2027, regulated distribution charges in the Czech Republic are calculated from the reserved power input and the highest measured quarter-hour load in each month. What this means for supply points at high and extra-high voltage, and how to check the impact in advance.

From 1 January 2027, the Czech Republic changes the way regulated charges for use of the distribution grid are calculated. The change applies to supply points and buildings connected at high voltage (HV) and extra-high voltage (EHV). The price of the electricity itself does not change. What changes is the basis from which the regulated part of the invoice is calculated.

What changes in 2027

Until now, HV and EHV supply points paid mainly for reserved capacity and for exceeding it. The new tariff structure is based on two figures:

  • the reserved power input set in the connection contract,
  • the highest measured quarter-hour load in the given month.

The second figure is new. The charge is no longer influenced only by the amount of electricity drawn, but also by the load profile. If a high maximum occurs in any quarter hour, it is reflected in the regulated charge for the whole month.

Why the rules are changing

The current capacity reservation rules were introduced almost twenty years ago. Since then, many supply points have kept a higher reserved power input than they use today. The distribution operator still has to keep that capacity available at all times, whether it is used or not. Part of the grid capacity is therefore blocked even though nobody needs it.

According to the Czech Energy Regulatory Office (ERÚ), the new tariff structure could release up to 3,300 MW of reserved power input, which is roughly 15 % of current grid capacity.

Example: two halls with the same consumption

The following example is a model one. Two production halls each draw 5 GWh of electricity a year.

In the first hall, the load is spread evenly across the day and equipment is started in sequence.

In the second hall, several energy-intensive machines are started at the same moment a few times a month. In those quarter hours the load is much higher than during the rest of the month.

Both halls have the same annual consumption, yet their regulated charges will differ under the new structure. The second hall will pay more because of its quarter-hour maxima.

Which supply points will pay more

The size of the operation does not matter. Higher charges can be expected at supply points that:

  • have a reserved power input well above what they actually need,
  • have irregular load peaks,
  • have not adjusted their reserved power input since it was contracted,
  • have no overview of their load profile.

Supply points with correctly set power input and a managed load will notice little change.

How to find out the impact on a specific supply point

The impact cannot be determined from the connection contract or from the latest invoice. Contract parameters, billing data, interval metering, load peaks and the rules of the new tariff structure have to be put together. Only their combination shows by how much the charge will change.

The part that is usually hardest to get is an overview of the load profile: when the maxima occur, which equipment was running at that time and how much of the reserved power input the supply point uses. Enmon displays quarter-hour data from supply points continuously, so this information is available before the first invoice under the new rules arrives.

What can be done

In most cases the future charges can be influenced. Depending on what the data shows, it may make sense to:

  • adjust the reserved power input in the connection contract,
  • spread the start-up of energy-intensive equipment over time,
  • change how equipment is controlled so that unnecessary peaks do not occur,
  • use battery storage or another technology that limits short-term maxima,
  • monitor the load diagram continuously and respond to changes in operation.

Who is affected

From 1 January 2027, the new tariff structure applies to approximately 25,000 supply points at HV and EHV level. Households and low-voltage supply points are not affected for now.

Experience from practice

The logistics group Geis monitors 18 sites in three countries in Enmon. Since the system was deployed, it has paid no penalties for exceeding reserved capacity. The quarter-hour maxima it watches today because of penalties will, from 2027, enter directly into the calculation of the regulated charge.

Anyone who wants to know the impact on their supply points should start the assessment before 1 January 2027. After that date, invoices will already be based on the new rules.

Frequently asked questions

Not the commodity. What changes is how regulated distribution charges are calculated. A supply point with a flat load diagram will barely notice the change, one with sharp peaks may pay more, even if both draw the same number of megawatt hours.

Not from 2027. The new structure targets high and extra-high voltage. Under the planned reform, low voltage follows in 2030.

No. An invoice shows consumption and contracted parameters, but not how the load behaves across quarter hours. That is exactly what decides the outcome from 2027.

Then it is worth comparing it with the actual load. If it was contracted for an operation that has changed since, you are paying for power input you do not use, and from 2027 the effect of quarter-hour maxima is added to that.

How much is quietly leaking at your sites?

Send us a few invoices and the number of buildings. An operations screening shows where to start.